Hello,children.
Have you completed the table given? Now, you can check your answer here.
Event started
|
Event ended
|
Duration
|
July 2008
|
December 2008
|
6 months
|
February 2009
|
March 2011
|
2 years and 2 months
|
26 June 2007
|
13 September 2010
|
3 years 2 months and 13 days
|
Solutions:
July
|
August
|
September
|
October
|
November
|
December
|
1 month + 1
month + 1 month + 1 month + 1 month +1 month
= 6 months
The
duration from July 2008 to December 2008 is 6 months.
February 2009 to
January 2010
|
February 2010 to
January 2011
|
February 2011 to
March 2011
|
1
year + 1 year + 2 months = 2 years and 2 months
The
duration from February 2009 to March 2011 is 2 years and 2 months.
26 June 2007
to
30 June 2008
|
1 July 2008
to
30 June 2009
|
1 July 2009
to
30 June 2010
|
1 July 2010
to
31 August 2010
|
1 September 2010
to
13 September 2010
|
|
1 year + 1 year
+ 1 year + 2 months + 13 days =
3 years 2
months and 13 days
The
duration from 26 June 2007 to 13 September 2010 is 3 years 2 months and 13
days.
Have a happy day.